Work Order Tracking – Assignments Overview

December 15, 2020

Last Updated on October 29, 2023 by maximosecrets

Contents

There is more to Work Assignments than you may think and naturally many Maximo practitioners look at Assignments as being a product of planning work or applying a Job Plan, which of course they are. But you can plan work in the Assignments tab of the Work Order Tracking application without using Job Plans or the Plans tab.

This article provides an overview of how the Assignments table window functions, all performed without creating a Job Plan or using the Plans tab of the Work Order Tracking application. The overview captures the main points from several other articles which provide the details, together stretching to more than 30 pages, too much for one article.

This overview is a summary of each article or section within those articles, and hence can be used to navigate from this overview to the detailed article. To get an overview of the Available Labor dialog or the action Reschedule/Unassign Assignments, you will need to reference multiple sections.

Simple Work Assignments in Work Order Tracking

A work assignment is a record that exists in the Assignments tab and Assignments table window of the Work Order Tracking application. I like to call it a work assignment because the term assignment may confuse this with using the fields in the Responsibility section at the bottom of the main Work Order tab, fields like Supervisor, Lead, Owner, Crew, etc. I prefer to think of these fields as providing “ownership” of the work order.

If you only assign by using the Responsibility fields, if you only determine “ownership”, then you cannot make much progress in using the Maximo Scheduler applications. If you use work assignments, then it is a relatively small step to make use of some of the Maximo Scheduler graphical applications. However, the Graphical Scheduling application does require you to use Job Plans and use the Plans tab of the Work Order Tracking application.

If you are currently assigning ownership but want to use the Maximo Scheduler then using the Assignments tab is a good first step to take, it gets you used to reviewing the work assignments and creating the data that it relies upon.

This first article introduces how to create simple work assignments, the sort of assignment that you might do for an emergency work order or call-out where there is no time to plan. In this scenario you are dispatching a labor or crew to a work order with an immediate scheduled start.

The main Assignment points from this article were: